Status of Water Tank Construction

11/3/2009

Inside of the tank
The work stand is used for the detector construction.

26/2/2009

Water filling test is ongoing.

05/02/2009

A spiral staircase was installed.

 

22/01/2009

From top of the tank

The cross bars are installed.

 

14/01/2009

From top of the tank

The ceiling plates will be installed.

 

06/01/2009

From top of the tank

The ceiling plate will be installed on the this frame

 

28/11/2008

The fifth board

The welding of the joint of the stainless steel board has started

 

21/11/2008

The fourth piece stainless steel board was piled up

20/11/2008

The third piece stainless steel board was piled up

They are connected temporally, and welded each other afterwards

20/11/2008

The second piece stainless steel board was piled up

18/11/2008

From top

18/11/2008

In the tank a work stand is installed to construct the detector

12/11/2008

The one piece of stainless steel board is piled up

7/11/2008

The bottom of the tank is installed